Search
Search
Close this search box.

United Group Infrastructure – Westdale Alliance Floating Baffles

Chatoyer was contracted to design, supply, deliver and install the 4 baffle systems for their Westdale Alliance project.

Project Overview

Date: February 2011

Location: Tamworth, New South Wales, Australia

Features Summary

Baffle length:3 x 170m long baffles with 4m skirt & 1 x 120m long baffle
Materials used:XR-5 Geomembrane, SS mounting hardware & HDPE anchoring systems
Floats: 
Solid molded closed cell polyethylene foam floats
Ballast: 
Lead ballast

Project Summary

  • Chatoyer were contracted to design, supply, deliver and install the 4 Westdale Alliance floating baffles 
  • A design was put together to accommodate the variation in normal operating level and maximum operating levels during maintenance periods
  • Installation of the baffle systems was completed in one week 

Hi there.

Want to get in touch?

Drop us a line

Login to your
direct reseller account